How many total miles of new physical barrier had CBP contracted for or completed by December 31, 2025?
Executive summary
By December 31, 2025, publicly available CBP documents and press releases show a clear but incomplete picture: at least about 116 miles of new physical barrier had been explicitly contracted (including recent Smart Wall awards and previously obligated contract miles), while the total of completed miles since January 20, 2025 is not stated in the cited materials and therefore cannot be reliably quantified from these sources alone [1] [2] [3].
1. What the records explicitly show about newly awarded contracts
A CBP national release in late 2025 lists five Smart Wall contracts awarded in November–December 2025 and specifies project-level barrier miles for several of them — Tucson 2 (19 miles primary and 19 miles secondary), Del Rio 3 (22 miles primary), and Laredo 1 (15 miles primary plus 16 miles of waterborne barrier) — which together account for at least 91 miles of new barrier or waterborne barrier tied directly to those contract awards [1]. That release also states the Smart Wall contract portfolio reached $8 billion but does not provide a single consolidated miles total for all awarded contracts, and it distinguishes detection-technology mileage (about 149 miles) from new barrier mileage [1].
2. Pre-existing contract obligations that add to the tally
Separately, DHS’s FY2025 border-barrier funding report notes approximately $577 million in previously held FY2020–FY2021 funds already obligated on contracts for the construction of roughly 25 miles of new border wall, which CBP is prioritizing toward current projects; those obligated miles therefore represent additional contracted work carried forward into the 2025 program [2]. Combining the clearly enumerated recent contract miles with the previously obligated 25 miles yields a minimum of about 116 miles that can be tied to contracts as of the end of 2025 from the documents provided [1] [2].
3. Planned projects are much larger but are not the same as contracted
CBP’s environmental assessments and planning documents filed in 2025 show many large “planned” projects — for example, CBP describes planning approximately 222 miles of barrier-system attributes in parts of Arizona (Tucson sector), 88 miles in El Paso/Hudspeth Counties, 142 miles of barrier-system attributes in Imperial/Yuma counties, and a 63-mile waterborne barrier project in Maverick County — but these materials are framed as planning or NEPA analyses and do not mean contracts were awarded or construction completed as of December 31, 2025 [4] [5] [6] [7]. CBP’s Smart Wall Map similarly separates “planned,” “under construction,” and “completed” mileage but the map content in the sources does not provide a single completed-mile total in the cited excerpts [3].
4. Completed miles: the public record in these sources is silent
CBP’s Smart Wall Map is described as showing completed mileage “since 1/20/2025,” but the excerpts provided do not include an explicit numeric total of completed miles as of the end of 2025; therefore the amount of new physical barrier actually finished by December 31, 2025 cannot be determined from the supplied documents alone [3]. CBP’s press release and environmental assessments discuss awards, planning, waivers, and attributes of barrier projects (lighting, fiber, cameras, roads) but do not publish a consolidated completed-miles figure in the excerpted materials [1] [4] [5].
5. How to read these numbers and what’s missing
The cautious, evidence-based conclusion from the materials provided is that at least ~116 miles of new physical barrier had been contracted for by year-end 2025 — a floor, not a cap — composed of recently awarded contracts that explicitly list ~91 miles and previously obligated contract work of ~25 miles [1] [2]. Planned projects described in CBP environmental documents would add hundreds more miles if executed [4] [5] [6] [7], but “planned” or “assessed” mileage should not be conflated with contracted or completed work without supporting contract award notices or completed-mileage reports, which are not present in the provided sources [3] [1].